While Townsville now begins the vast task of flood recovery, many construction projects around Australia are constantly facing a degree of flood risk from either storm-related flash flooding or widescale riverine flooding.
Founding principal of聽consulting, Steven Molino, tells聽Jobsite聽that understanding the risks of flooding at the early project stages is essential. It might appear we are having more floods more often considering the number of times both flash flooding and riverine flooding hit the headlines.
鈥淭he problem hasn鈥檛 changed. What has changed is the value of assets we have in areas prone to flood,鈥 said Molino.
When Overflow Is Inevitable
We have only been building in many areas for 200 years or less, which may also mean there is a lack of experience to inform the risk picture. Couple this with Australia鈥檚 highly variable rainfall, older stormwater systems in urban areas designed for lower volume UK rainfall patterns, and the tendency to build near waterways for their many benefits, such as water supply and transport鈥攁nd you end up with a risk-laden scenario.
Molino says it is not possible to design every stormwater system to have the capacity to take any possible rainfall event. Therefore, we need to accept they are likely to overflow at some point.
Flood Resilience Strategies
There are some guidelines available to developers, planners, designers and builders; they may serve as a reference for best practice flood resilience strategies. These guidelines include the National聽from the Australian Institute for Disaster Resilience and the NSW. Brisbane City Council also created聽and management resources.
The rules about whether a development must adhere to guidelines or not vary from state to state. In Western Australia, South Australia and Tasmania, for instance, adherence to the national guidelines is not required, Molino says.
What builders, developers and designers should be looking for is information specific to a site鈥檚 degree of flood risks鈥攚hat type of flooding is possible, the likely frequency, and the predicted water levels and flows.
In Victoria, Molino says, the local Catchment Management Authorities are the best place to start with gathering that intelligence.
In other states, local councils are the key. However, he warns the comprehensiveness of information can vary from council to council. Moreton Bay Regional Council in Queensland makes that information very accessible, with an on-line flood risk mapping database that can be freely accessed, but not everyone is as accommodating. In other states, the council may tell you nothing more than that there are planning controls that have been put in place due to a known flood risk.
Managing the Consequences
From understanding the risks, the next step is to think about what the consequences of flooding could be.
Firstly, Molino says, you should consider the risks to the finished project. You need to think about the impacts on the building itself and any plant and equipment exposed to flood waters. The building may also cause water to flow towards neighbouring buildings or infrastructure and damage them.
鈥淒esigners are good at finding ways to manage these risks according to best practice.鈥
Then there are the risks to people occupying or visiting finished development. Molino says this means taking into account people鈥檚 possible behaviours.
Considerations include 鈥渨hat if the street becomes a river?鈥 and 鈥渨hat if people come into the building and get trapped?鈥
Where projects often come to grief is these things haven鈥檛 been considered. Then, the Development Application is rejected by consent authority until the risks are managed.
Molino says more and more project proponents are finding they have to consider flooding but often do so once the design is extremely advanced and making modifications is costly. Flood risk to projects during construction he says is 鈥渞arely considered,鈥 partly because the construction timeframe is relatively short.
In fact, Molino has consulted on projects where the project design, construction timeframe and location combined together created a real risk that needed managing.
As an example he gives is a site next to a stormwater canal which was likely to overflow in a one in five-year storm event. While the design had considered and adapted to managing the risks of a 100-year flood event, part of the solution was a four-storey basement car park that would be accessible via a car lift and would be sealed to prevent water ingress.
Molino pointed out that having a four-storey basement excavation next to a canal that has a 50/50 chance of overflowing during the two-year basement construction period was a risk that needed to be addressed.
Assessing High and Low Risks
In general, there are a number of practical things projects at risk of storm-related flash flooding, tidal flooding, or riverine flooding need to consider.
The first is gaining a thorough understanding of the likelihood and consequences of the risks and make decisions about how acceptable the consequences might be. For example, if the worst-case scenario is some silt fences might be flattened, that might be considered an acceptable risk, Molino explains. 鈥淏ut if you have earth moving equipment that might be damaged, you might think about how to protect that.鈥
Recently, he consulted a project where there were high risks at part of the site. In that case, the most sensible thing to do was to change the planned site layout so that the plant and materials stockpile were located at the highest part of the site.
As well as the potential magnitude of damage to assets, materials and equipment, considering the risk to the workforce also matters. Even at the tender stage, it would be sensible for builders to identify and understand flood risks and build a margin for any mitigation or protective equipment into the budget, Molino says.
鈥淵ou can鈥檛 change the probability of flooding鈥攂ut you can change the likely consequences.鈥